CYCAS Stratford, London

Holiday-Inn300x200

Client

CYCAS – Holiday Inn & Staybridge Suites, Stratford, London


Project

New Build Hotel


Main Contractor

Westfield


Design & Build

Halsall - M & E


Contract Period

30 weeks


Completion Date

2012

CYCAS – Holiday Inn & Staybridge Suites, Stratford, London

New Build 350 Room Hotel for CYCAS – Holiday Inn and Staybridge Suites, Stratford, London, comprising of the installation, testing and commissioning of the following M&E Services:

• HV Distribution – 11 kv
• LV Distribution – 400 v
• Generation
• Castel Interlock System
• Mechanical Plant And Control Panel Supplies
• Lighting Installation
• Feature Lighting Installation
• External Lighting Installation
• Lighting Controls
• Emergency Lighting Systems
• Small Power Installation
• Intruder Alarm System
• CCTV System
• Fire Alarm System
• Telephone System
• Micros Fidelio Installation
• Disabled Refuge System
• Disabled Alarm System
• Disabled Call – Carpark System
• Structured Cabling Installation
• Data & IT Installation
• Public Address System/Background Music
• Domestic Hot and Cold Water Services Installation
• H & V Controls
• Heating & Ventilation
• Fan coil Air Conditioning Installation
• Above Ground Drainage Installation
• LPHW Pipework Installation
• External Gas
• Mains Water
• Sanitaryware Installation
• Achieved BREEAM Excellent Standard